Client
London Luton Airport Operators Ltd
Project Value
£16.7 million
Services Provided
Cost Management, Contract Advice and Procurement Advice
About the project
The project comprised landside civil engineering works bringing improvements to access, airport highway and external pedestrian circulation and parking facilities which were required to support the terminal expansion project.
The works included:
- Dualling of the Airport Way approach road from Percival Way roundabout to the Central Terminal Area
- Improvements to the short-stay car park were required, including new road construction and resurfacing of the existing car park
- Improvements to the Central Terminal Area and public transport areas adjacent to the terminal were undertaken, including a new coach and taxi drop-off zone, a new private vehicle drop-off zone and the provision of 18 dedicated bus parking bays
- Construction of an enclosed pedestrian walkway over the access road adjacent to the Terminal