Go Back
Client
London Luton Airport Operators Ltd
Project Value
£70 million
Services Provided
Cost Management, Contract Advice and Procurement Advice
About the project
The project comprised the reconfiguration and expansion of both landside and airside terminal expansion and refurbishment works, increasing floor space by approximately 25% and creating a more integrated and ergonomic building.
The works included:
- The construction of an infill building.
- A new two-storey pier (Pier B) and associated link building.
- Construction of infills to existing Pier A.
- Extension and relocation of the Immigration Hall.
- Reconfiguration of duty-free area.
- Refurbishment and extension of domestic and international arrivals.
- Relocation and extension of passenger screening area.